6 Sept 2022
BLUE OCEAN FRONTIER SDN. BHD. ASTON VILLA SDN. BHD.
- Citation
- WA-22NCvC-460-07/2019 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-22NCvC-460-07/2019 (Mahkamah Tinggi)
Plaintiff failed to prove on the balance of probabilities that it had completed, tested, commissioned and handed over all scope of works as required by the PO and Settlement Agreement; payment obligations under the Settlement Agreement (Clause 8(c)) only arose after completion/testing/commissioning/handover and therefore did not mature; Plaintiff's invoices were premature and interest calculation was improper; Plaintiff's SST claim failed due to cancelled registration; Defendant's counterclaim for losses caused by Plaintiff's delay was allowed in part. Net result: Defendant ordered to pay Pla…