8 Jan 2026
1. ) YONG KOK YEAP 2. ) FANG CHEE PENG URUSWAJAR CONCRETE SDN BHD
- Citation
- BA-12B-35-04/2025 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-12B-35-04/2025 (Mahkamah Tinggi)
The appeal was dismissed because the original Continuing Guarantee & Indemnity, as produced and inspected, established the defendants as guarantors for MKP Builders; there was no admissible evidence that the guarantee was for Element Flash; the contract terms made the guarantors principal debtors and liable independently of proceedings against MKP Builders; the plaintiff's signed statement of indebtedness was conclusive as to the amount owed; accordingly the High Court upheld the Sessions Court decision and awarded costs.