15 Aug 2025
COVA DESIGN & CONTRACT SDN. BHD. INTBUILD CONCEPT SDN. BHD.
- Citation
- BA-12BNCC-4-03/2025 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-12BNCC-4-03/2025 (Mahkamah Tinggi)
The High Court found the trial judge was plainly wrong for failing to consider contemporaneous documentary evidence establishing that the agreed completion date (15.3.2020) was missed and actual completion for the disputed 152 units occurred on 13.7.2020; under the clear contract terms the respondent was entitled to LAD and to recover reasonable repair costs for defects within the 24‑month defect liability period; accordingly the Sessions Court decision was set aside and the specified monetary awards, CTOS removal and costs were ordered.