12 Jun 2023
1. ) Blue Green Network Sdn Bhd 2. ) Ng Wee Ong 3. ) Ho Hui Ping 4. ) S. Latha Devi A/P K P Rajasekharan Nayar 5. ) Chong Kim Lan 6. ) Chan Siew Leong 7. ) Lai Yin Keng 8. ) Lum Wen Foo 9. ) Kook Wai Ying 10. ) Low Yeong Take 11. ) Hew Lai
- Citation
- BA-22NCvC-244-06/2021 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-22NCvC-244-06/2021 (Mahkamah Tinggi)
The Court awarded the Plaintiffs RM1,778,360.17 as combined liquidated damages for late delivery of vacant possession and late completion of common facilities, holding the period of delay to be computed 36 months from payment of deposit/booking fee to delivery or deemed delivery; interest and costs were awarded and the Defendant's counterclaim for exemplary damages was dismissed; withdrawn claims on strata title delays were struck out with no liberty to file afresh.