31 Dec 2024
DFE UNIQUE WMG & NAEL ENTERPRISE
- Citation
- JA-A52NCvC-62-04/2021 (Mahkamah Sesyen)
- Court
- Sessions Court
- Case number
- JA-A52NCvC-62-04/2021 (Mahkamah Sesyen)
Plaintiff failed to prove its claim; plaintiff is bound by the Service Order including Part 1/Part 2 and repudiated the joint venture by withdrawing mid-project; defendant proved loss reasonably foreseeable from plaintiff's breach and is entitled to RM240,242.06 damages plus exemplary damages of RM20,000; plaintiff's special damages claims were not pleaded or proved; documentary evidence contrary to contemporaneous documents was given no weight and certain self-serving documents excluded under s73A(3).