28 Oct 2022
CONCRETE IMPACT SDN BHD CONDOLINK SDN BHD
- Citation
- WA-22C-13-01/2021 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-22C-13-01/2021 (Mahkamah Tinggi)
On the balance of probabilities the court found the Plaintiff completed the subcontract works by the end of EoT No.2 (15.5.2014); joint measurements and documentary evidence supported Plaintiff's quantities; Defendant failed to prove delay or establish entitlement to LAD; Plaintiff entitled to part of its claimed quantum after accepted deductions — RM171,254.41 plus interest and costs; Defendant's counterclaim for LAD dismissed.