27 Apr 2022
Lakefront Residence Sdn Bhd Lam Keng Fong
- Citation
- BA-12ANCvC-18-02/2022 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-12ANCvC-18-02/2022 (Mahkamah Tinggi)
The purported 18‑month extension granted by the Controller/Housing Ministry was ultra vires and void, the statutory 36‑month delivery period under Schedule H applies, LAD is computed from the booking/payment date, and the defendant failed to show any triable defence; therefore summary judgment for LAD was properly granted and the appeal is dismissed.