27 Aug 2021
ASTON STAR SDN BHD ZUMO ENGINEERING (M) SDN BHD
- Citation
- WA-22C-102-11/2018 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-22C-102-11/2018 (Mahkamah Tinggi)
The contract was governed solely by the Letter of Award; the Defendant's alleged May 2014 quotation was fabricated and given no weight; Payment Certificates were interim only and final payment required re-determination; the Defendant failed to keep adequate contemporaneous records for transient scaffolding works so its volumetric claims were unreliable; the court accepted the conservative expert valuation prepared for the Plaintiff (PW8/PW7) together with validated manpower hours (DW3) yielding a re-determined contract value, resulting in a net overpayment of RM65,496.98 payable to the Plaint…