10 Mar 2022
CRCC MALAYSIA BERHAD INTELLIGENT M&E SDN BHD
- Citation
- WA-22C-55-06/2019 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-22C-55-06/2019 (Mahkamah Tinggi)
Defendant proved, on the balance of probabilities, that specified work and variation orders were instructed by the Plaintiff (including by Site Instructions and oral approvals), were performed and documented, and Plaintiff breached its contractual obligation to certify and pay within 45 days; accordingly the court allowed parts of the Defendant's counterclaim for the value of proven work and variations and awarded interest at 5% per annum from the relevant due dates, while finding Plaintiff validly terminated the EWSSC and dismissing claims of repudiation and unproven loss items; netting of t…