13 Apr 2026
International Shipcare Sdn Bhd 1. ) Sabenajadi Sdn Bhd 2. ) Petronas Dagangan Berhad 3. ) Mohd Amin Bin Mohd Shukor
- Citation
- WA-22NCC-867-12/2025 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-22NCC-867-12/2025 (Mahkamah Tinggi)
The claim against the 2nd and 3rd Defendants is plainly unsustainable because there is no contractual nexus between Plaintiff and D2/D3 and the 2nd Defendant fully discharged its contractual obligations by paying the 1st Defendant the entire agreed sum; consequently there is no unjust enrichment or juristic gap to remedy under Section 71, promissory estoppel and fraud are insufficiently particularised, and the 3rd Defendant acted in his representative capacity so no personal liability is pleaded; therefore the pleadings against D2 and D3 are struck out.