CONDOLINK SDN BHD 1. ) SDB PROPERTIES SDN BHD 2. ) INTA BINA SDN BHD PIHAK KETIGA ELKA ELZA LEGACY SDN BHD
- Citation
- BA-22NCvC-327-07/2025 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-22NCvC-327-07/2025 (Mahkamah Tinggi)
The Statement of Claim failed to plead material facts linking the First Defendant to the alleged trespass; absent pleaded control, authorisation or assumption of responsibility, the independent contractor principle applies and no non-delegable duty was established; therefore the claim against the First Defendant is plainly unsustainable and an abuse of process, justifying strike out under Order 18 r.19 ROC.