12 Aug 2022
S5 SYSTEM SDN BHD TRIDIMAS SDN BHD
- Citation
- BA-22NCvC-64-02/2021 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-22NCvC-64-02/2021 (Mahkamah Tinggi)
The MNDA is the sole binding written agreement between the parties and, read within its four corners (including an entire agreement clause and clause permitting termination of negotiations), negates any enforceable teaming agreement or obligation to appoint the plaintiff as PMSP; the statement of claim therefore fails to disclose a reasonable cause of action and is scandalous, frivolous and an abuse of process, warranting strike out under O18 r19(1)(a),(b) and (d) ROC.