SYARIKAT LEAN HUP (LIEW BROTHERS) SDN BHD V. CHEOW CHONG THAI
- Citation
- SYARIKAT LEAN HUP (LIEW BROTHERS) SDN BHD V. CHEOW CHONG THAI
- Court
- Malaysian court
The agreement was rectified for mutual mistake of law to conform with the 1982 Regulations: completion period is 24 months and agreed damages are 10% p.a.; vacant possession occurred upon connection of water and electricity (20 February 1986); damages assessed from the statutory expiry date (29 July 1984) to 20 February 1986 (569 days) at 10% of the purchase price, producing the monetary award and interest; appeal dismissed.