25 Feb 2026
FLOWFUEL SDN BHD HARBANS SINGH A/L SADHU SINGH BUKAN PIHAK-PIHAK 1. ) CHEVRON MALAYSIA LIMITED 2. ) Kementerian Perdagangan Dalam Negeri dan Hal Ehwal Pengguna
- Citation
- BC-A52NCvC-17-07/2022 (Mahkamah Sesyen)
- Court
- Sessions Court
- Case number
- BC-A52NCvC-17-07/2022 (Mahkamah Sesyen)
The court found on objective evidence that the stamped Sub-Lease and Lease Agreements were final and validly executed; the defendant breached conditional obligations by failing to register and by terminating; under s66 Contracts Act 1950 the defendant must restore the RM36,000 advantage received; only proven legal fees of RM16,805 were recoverable as special damages; defendant's counter-claim failed for lack of proof.