EVERGREEN FUTURE HOME BUILDERS 1. ) TRIBUNAL TUNTUTAN PENGGUNA 2. ) JAI BHAVANI
- Citation
- BA-25-27-04/2025 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-25-27-04/2025 (Mahkamah Tinggi)
The court allowed the Attorney General's objection and dismissed the leave application because it was filed 93 days late beyond the three-month limit in O.53 r.3(6) and the applicant failed to establish good reason to extend time under O.53 r.3(7); the 2nd Respondent was not entitled to participate at the ex parte leave stage absent an invitation.