28 Jan 2026
Syed Muhammad Hafiz Bin Syed Ahmad YTS ARCHITECTURE SDN BHD
- Citation
- BA-12BNCC-23-12/2025 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-12BNCC-23-12/2025 (Mahkamah Tinggi)
Extension of time refused because the 48‑day delay was substantial, the defendant's explanation attributing delay to former solicitors was not a cogent reason under established precedent, the defendant failed to demonstrate a meritorious appeal and had shown lackadaisical conduct at trial, and the court must protect the timetable and oppose prejudice to the respondent.