10 Feb 2021
CHONG CHIM TIONG MAMMOTH EMPIRE LAND SDN BHD
- Citation
- B52NCVC-234-09-2020 (Mahkamah Sesyen)
- Court
- Sessions Court
- Case number
- B52NCVC-234-09-2020 (Mahkamah Sesyen)
Plaintiff satisfied Order 14 prerequisites and established a prima facie case; defendant failed to demonstrate any triable issues or provide documentary evidence to rebut liability. The purported extension of time by the Housing Ministry was invalid under Ang Ming Lee and related authority and could not vary the statutorily prescribed Schedule H terms. Plaintiff retained locus standi despite the financier charge and LAD computation correctly commences from payment of booking fees; summary judgment therefore entered for plaintiff for RM806,219.57 plus 5% p.a. from 29.9.2020 and costs RM4,000.