31 Oct 2022
PERBADANAN STADIUM MALAYSIA MILESTONE PRODUCTION SDN BHD
- Citation
- BB-A71NCvC-237-04/2021 (Mahkamah Majistret)
- Court
- Magistrates' Court
- Case number
- BB-A71NCvC-237-04/2021 (Mahkamah Majistret)
On the balance of probabilities the Plaintiff proved the debt via the rental agreement, invoice dated 16/4/2015, meter readings, credit note and payment vouchers; the court held the cause of action accrued on issuance of the invoice on 16/4/2015 so the action filed 13/4/2021 was within the six‑year limitation period; discrepancies over meter readings were insufficiently proved by Defendant and lacking expert evidence; the contract was treated as complete for salient terms. Therefore Defendant liable to pay RM 53,622.95 and claim allowed with costs on scale.