6 Sept 2023
BM CITY REALTY & CONSTRUCTION SDN BHD MERGER INSIGHT (M) SDN BHD
- Citation
- WA-24C(ARB)-28-06/2023 (Mahkamah Tinggi)
- Court
- ARB
- Case number
- WA-24C(ARB)-28-06/2023 (Mahkamah Tinggi)
The originating summons was dismissed because it was filed more than ninety days after receipt of the award in breach of the mandatory time limit in section 37(4) of the Arbitration Act 2005 and was not filed with the affidavit required by Order 69 rule 4(2) of the Rules of Court 2012, with no explanation or application for extension of time provided.