25 Jul 2025
1. ) SEMASA SENTRAL SDN BHD (P dalam Tindakan Asal & D1 dalam Tuntutan Balas) 2. ) Jewel Builders & Resources (M) Sdn Bhd 1. ) GLOBAL FUSION SDN BHD 2. ) Malaysia Resources Corporation Berhad 3. ) MRCB Builders Sdn Bhd (D3 dalam Tuntutan Ba
- Citation
- WA-22NCvC-320-05/2024 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-22NCvC-320-05/2024 (Mahkamah Tinggi)
The court found D3 and D4 had not taken disqualifying steps in the proceedings and that the arbitration clauses in the Letters of Award covered the dispute, but in the exercise of its discretion under s 10(2) the court dismissed the stay applications because D3 and D4 failed to propose or justify conditions to address the reality of multiple non‑parties (consent unlikely), selective invocation of arbitration would cause procedural injustice, risk of duplicative evidence and inconsistent findings, and therefore a stay was inappropriate.