15 Mar 2021
E&C PRO SDN BHD (NO. SYARIKAT : 1187683 – A) ECO WORKS ENGINEERING SDN BHD (NO. SYARIKAT : 1226171 – U)
- Citation
- BA-12ANCC-68-10/2020 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-12ANCC-68-10/2020 (Mahkamah Tinggi)
Plaintiff met preliminary Order 14 requirements; defendant failed to produce contemporaneous documentary evidence or precise timely complaints to establish a bona fide triable issue; defendant's late disputes and part payments gave rise to estoppel/non-query and its email amounted to an admission; counterclaim lacked supportive contemporaneous evidence — thus summary judgment for RM607,214.60 was properly entered and was affirmed on appeal.