18 Oct 2023
ANJUNG HIJAU SDN BHD 1. ) ASSOCIATED BUILDERS & CONTRACTORS SDN BHD 2. ) ZON DESIGN REKABINA SDN BHD 3. ) AHMAD JAAFAR BIN AZIZUL RAHMAN
- Citation
- WA-22C-83-08/2017 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-22C-83-08/2017 (Mahkamah Tinggi)
On the evidence and legal principles the court found the plaintiff failed to prove non-compliance or impropriety: D1 submitted the requisite written notice within 28 days; ZNA's instructions were Relevant Events; D2 exercised fair and reasonable discretion under PAM 2006 when granting EOT1, EOT2 and EOT3; no evidence of conspiracy was adduced; plaintiff failed to prove loss for LAD and failed to particularise or produce supporting proof; D1 proved the unpaid certified balance. Therefore plaintiff's claims dismissed and D1's counterclaim succeeded for the specified balance with interest and co…