  • 26 Jul 2024

    LATEX FORM SDN BHD IVORY GLOVE SDN BHD

    Citation
    BA-22NCvC-520-12/2022 (Mahkamah Tinggi)
    Court
    High Court
    Case number
    BA-22NCvC-520-12/2022 (Mahkamah Tinggi)

    On the balance of probabilities the court found the contract required concurrent installation and that Plaintiff had substantially performed (approx. 95%, 70%, 60%), Defendant breached the payment schedule causing suspension; Plaintiff entitled to payment of RM4,040,000 for completion of machine one and must complete, Defendant's counterclaims for liquidated damages, loss of profit and storage were not proven and are dismissed; Plaintiff awarded interest at 5% p.a. on RM4,040,000 from filing date and costs RM15,000.