15 Oct 2025
1. ) KUMAR A/L PARAMESWARAN 2. ) JAYANALINI A/P R MUNIYANDI ERA UNIVERSE DEVELOPMENT SDN BHD
- Citation
- JA-A52NCvC-318-10/2024 (Mahkamah Sesyen)
- Court
- Sessions Court
- Case number
- JA-A52NCvC-318-10/2024 (Mahkamah Sesyen)
Court held s35 Covid-19 Act 2020 did not apply because contractual delivery date (6.3.2020) predated the exclusion period; plaintiffs were entitled to enforce the LAD clause calculated on the contract purchase price RM648,000; defendant failed to raise a reasonably arguable defence or triable issues, so summary judgment under Order/Rule 14 was appropriate; implied consent and need to prove actual loss were rejected as defences.