16 Mar 2021
CHIN YONGQIN (NRIC NO.: 901029-01-5643) PROSPER PLUS INDUSTRY SDN BHD (COMPANY NO.: 251713-A)
- Citation
- JA-11ANCVC-17-09/2020 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- JA-11ANCVC-17-09/2020 (Mahkamah Tinggi)
The Controller's grant of extensions under regulation 11(3) HDR 1989 is invalid per Ang Ming Lee, therefore the original 36‑month completion period in the Schedule H contract applies; LAD is calculated from date of payment of the booking fee per the Federal Court in PJD Regency; rebate/discount cannot be used to reduce the base for LAD; respondent failed to raise triable issues to defeat summary judgment.