7 Nov 2025
PENGERANG REFINING COMPANY SDN BHD 1. ) SINOPEC ENGINEERING (GROUP) CO LTD 2. ) SINOPEC ENGINEERING GROUP MALAYSIA SDN BHD
- Citation
- W-02(C)(A)-565-04/2025 (Mahkamah Rayuan)
- Court
- C
- Case number
- W-02(C)(A)-565-04/2025 (Mahkamah Rayuan)
The Court found the appellant's demand on the performance bond was unconscionable because the facility had been completed and was operating, the appellant deliberately withheld the approved performance test report to avoid issuing provisional acceptance and sought to recover delay damages after benefiting from operation; consequently the High Court's grant of interim injunction and refusal to set aside the ex parte order were correct and both appeals were dismissed.