6 Mar 2020
MUHAMMAH ZAHIR SANJAY BIN ABDULLAH MENTARI DHUHA SDN BHD
- Citation
- WA-12ANCVC-104-05/2019 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-12ANCVC-104-05/2019 (Mahkamah Tinggi)
The plaintiff proved a prima facie case that the defendant, as stakeholder, undertook to refund RM380,000 if no contract was executed within three months; the defendant failed to show any meritorious triable issue or defence on the merits; therefore summary judgment under Order 14 r.2 ROC 2012 was proper and the striking out application under Order 18 r.19 ROC 2012 was redundant and unsustainable. The High Court dismissed the appeals and affirmed the Session Court’s orders.