26 Jul 2024
AGILE PJD DEVELOPMENT SDN BHD CHINA CONSTRUCTION YANGTZE RIVER (MALAYSIA) SDN BHD
- Citation
- WA-24C-37-03/2024 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-24C-37-03/2024 (Mahkamah Tinggi)
The court held the setting aside application failed because the CNC was never before the Adjudicator and Agile had opportunities to produce it; no breach of natural justice or clear and unequivocal error was shown; the stay was refused because CCYR is financially secure and CIPAA’s scheme favors speedy recovery; accordingly enforcement of the Adjudication Decision was granted.