24 Jul 2025
CRYSTAL CLEAR CLEANING SDN BHD AEON CO. (M) BHD
- Citation
- WA-22NCvC-121-02/2020 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-22NCvC-121-02/2020 (Mahkamah Tinggi)
The termination was invalid because the Defendant failed to prove mutual agreement to terminate, failed to comply with the contract's prescribed pre-termination procedures in the annexed schedule (warnings, penalties, supporting documents), and by continuing performance after alleged breaches effectively waived the right to terminate; therefore Plaintiff entitled to contractual relief for the remaining term and costs.