27 Jan 2026
ATM DEVELOPMENT SDN BHD (DALAM PENYELESAIAN) PEMBINAAN MELIMA (M) SDN BHD
- Citation
- WA-22C-84-11/2022 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-22C-84-11/2022 (Mahkamah Tinggi)
The Court found the Turnkey Contract obligated the Defendant to procure CPC and CCC by 31-12-2019; the Architect's CPC of 31-12-2019 was defective because essential infrastructure works (final road wearing course, telecommunication and electricity connections) were incomplete; Defendant breached the contract and is liable for proved LAD and certain proven prolongation losses; Plaintiff entitled to net judgment of RM2,153,173.08 plus 5% p.a. interest and costs; Defendant's counterclaim dismissed.