25 May 2023
GROUPLITE ENGINEERING SDN BHD 1. ) SKT CONSTRUCTION SDN BHD 2. ) GAN KIM KENG 3. ) ONG KHAM TOO
- Citation
- DA-22C-1-06/2022 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- DA-22C-1-06/2022 (Mahkamah Tinggi)
Plaintiff satisfied the procedural prerequisites for summary judgment under Order 14 and established a prima facie case supported by invoices, account statements, correspondence and an executed joint and several guarantee; defendants failed to produce particularized evidence or credible facts to show a bona fide triable issue (their challenges were general denials or implausible contentions), therefore summary judgment was appropriate for the amount claimed and costs were awarded.