19 Apr 2024
1. ) NIK JAMALULAI BIN NIK MAN 2. ) ALIAS BIN MANSOR 3. ) TAN FOONG LUEN 1. ) CONLAY CONSTRUCTION SDN BHD 2. ) CHU CHEE CHOON
- Citation
- NA-22NCvC-86-10/2019 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- NA-22NCvC-86-10/2019 (Mahkamah Tinggi)
The letter dated 20.12.2018 was held void and unenforceable because its consideration involved lobbying/influencing government (contrary to public policy and potentially unlawful) and was vague/uncertain; plaintiffs failed to prove they performed the contractual negotiation; evidence established the contract price was reduced; accordingly plaintiffs' claims failed and defendants' counterclaim succeeded, with restitution/costs consequences under s66 and ordinary principles of costs.