5 Jul 2024
TANJUNG OFFSHORE SERVICES SDN BHD 1. ) VME PROCESS SYSTEMS MALAYSIA SDN BHD 2. ) VME PROCESS ASIA PACIFIC PTE LTD
- Citation
- WA-22IP-40-09/2022 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-22IP-40-09/2022 (Mahkamah Tinggi)
The JSA was a contingent contract dependent on conditions precedent in clause 2.3 (notably Petronas releases) which were not fulfilled within a reasonable time and not procured because the 1st defendant did not accept Petronas' conditions; therefore the JSA and the IPPA (which was inextricably linked to the JSA) are null and void and the Bayan Settlement Sum (USD5,500,000) must be returned; additionally the July 2020 letters contained false statements of fact that were defamatory and constituted unlawful interference with the plaintiff's trade, entitling the plaintiff to injunctive relief, an…