19 Nov 2025
CHEAH WENG SENG 1. ) CHERAS PROPERTY SDN BHD (SEBELUM INI DIKENALI SEBAGAI NUSMETRO ARTE SDN BHD) 2. ) ASIAMEGA CAPITAL SDN BHD PIHAK YANG DIGARNIS 1. ) MALAYAN BANKING BERHAD 2. ) MAYBANK ISLAMIC BERHAD
- Citation
- WA-A54-144-10/2023 (Mahkamah Sesyen)
- Court
- Sessions Court
- Case number
- WA-A54-144-10/2023 (Mahkamah Sesyen)
Defendants failed to prove that the delay was excused by force majeure or external causes and failed to mitigate or show steps taken; the 31.5.2023 letter did not satisfy the SPA requirement for immediate notice of delivery and therefore delivery occurred only on 4.8.2023 producing a 303‑day delay; LAD is payable calculated on the SPA sale price (RM36,791.00) and rebates are not deductible; both defendants are liable and plaintiff is entitled to costs RM5,000.00.