1 Mar 2024
ESA JURUTERA PERUNDING SDN. BHD. Universiti Malaya (UM)
- Citation
- W-01(IM)(C)-105-03/2023 (Mahkamah Rayuan)
- Court
- IM
- Case number
- W-01(IM)(C)-105-03/2023 (Mahkamah Rayuan)
The Court of Appeal held that on the facts the defendant had not taken other steps amounting to an unequivocal waiver of the arbitration clause: its requests for extensions and service of a Notice to Produce were preparatory, it expressly reserved rights, filed notice of arbitration and a stay application promptly, and only filed defence after court compulsion; therefore s.10(1) required a stay and referral to arbitration.