PEMPETISYEN ELIXIR PROJECTS SDN BHD JHE CONSTRUCTION (M) SDN BHD
- Citation
- JA-28NCC-104-07/2024 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- JA-28NCC-104-07/2024 (Mahkamah Tinggi)
Enclosure 27 (stay) was allowed because the respondent had earlier-filed proceedings challenging the adjudication order and applications to set it aside and enforcement was not yet obtained, meaning the adjudication order had not attained finality and a bona fide dispute existed; therefore continuing the winding-up would risk breach of natural justice and prejudice the respondent, justifying a stay pending disposal of the earlier suit (JA-22C-3-05/2024).