2 Sept 2020
Jabar Khan @ Yasser Arafat bin Napi Jebcon Sdn Bhd
- Citation
- BA-24NCvC-64-01/2020 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-24NCvC-64-01/2020 (Mahkamah Tinggi)
Developer could not claim pre-JMB service charges from the successful bidder because assignment/auction did not transfer liabilities; on formation of the Joint Management Body the rights to collect such charges vested in the JMB; the developer had no lien to withhold the strata title and was obliged to execute transfer; additionally the developer's claim for the historical charges was time-barred under the Limitation Act.