10 Sept 2019
SRI DAMANSARA SDN BHD 1. ) VOON KUAN CHIEN 2. ) TRIBUNAL TUNTUTAN PEMBELI RUMAH
- Citation
- W-01(A)-17-01/2019 (Mahkamah Rayuan)
- Court
- A
- Case number
- W-01(A)-17-01/2019 (Mahkamah Rayuan)
The Court upheld the Tribunal and High Court: time for calculating late delivery damages runs from the date the booking fee (deposit) was paid where SPA execution was delayed; the purchase price for liquidated damages is the price stated in the SPA; collection of payments before signing the prescribed Schedule H SPA contravenes Regulation 11(2) and developers cannot circumvent statutory protection by credit notes or back‑dated SPA dating; no basis for judicial review was established.