6 Jun 2024
Icon City Development Sdn. Bhd. (DAHULU DIKENALI SEBAGAI SIERRA PENINSULAR DEVELOPMENT SDN. BHD.) 1. ) Daniel Hong Tiang Jin 2. ) Lim Siew Eng
- Citation
- WA-11BNCvC-31-04/2023 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-11BNCvC-31-04/2023 (Mahkamah Tinggi)
The SPA was ambiguous as to commencement of the 42-month period; construing ambiguity against the drafter (the developer) and applying the intention that the 42 months runs from approval of building plans, the court held the period commenced on 2 August 2012, making the delivery on 6 October 2016 a delay of 246 days; the magistrate's award for LAD was correct and the appeal was dismissed with costs.