17 Aug 2023
1. ) SMOOTH ACHIEVEMENT SDN BHD 2. ) CHONG KIM FOO 3. ) HYPER INDUSTRIAL AUTOMOTIVE SDN BHD 4. ) KUA SWEE KIAT 5. ) KUA SWEE KEONG 6. ) SWISSMA BUILDING TECHNOLOGIES SDN BHD 7. ) PLY-MART SDN BHD 1. ) CEKAL UNGGUL SDN BHD 2. ) JURUTERA PERU
- Citation
- BA-22NCvC-283-06/2018 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-22NCvC-283-06/2018 (Mahkamah Tinggi)
Vendor's contractual duty under Clause 11.2 to provide infrastructure includes ensuring steps are taken to have utilities laid to the land boundary and completion of M&E where applicable; entitlement to LAD depends on whether vacant possession was delivered after the contractual period (including extensions); Certificate of Practical Completion issued by the civil consultant was not shown to be issued negligently and thus Defendant 2 is not liable; where purchasers failed to make progressive payments vendor is entitled to counterclaims for unpaid sums with contractual interest under Clause 3.…