30 Oct 2022
RUBINO INDUSTRY SDN BHD C.E.L. CONSTRUCTION SDN BHD
- Citation
- JA-A72NCC-321-02/2020 (Mahkamah Majistret)
- Court
- Magistrates' Court
- Case number
- JA-A72NCC-321-02/2020 (Mahkamah Majistret)
On the balance of probabilities Plaintiff established delivery and acceptance of the marble in good order by signed delivery notes, supporting documents and witness evidence; Defendant's defect allegations arose only after the writ, relied on hearsay and uncorroborated witnesses, installation was excluded from the quotation, and therefore Defendant is liable for the outstanding debt; counterclaim and set‑off were dismissed.