9 Jul 2020
AMZED DEVELOPMENT SDN BHD 1. DATO' MAT JAHYA BIN HUSSIN 2. DATIN NAIMAH BINTI JAAFAR
- Citation
- R-02(NCVC)(W)-1356-07/2019 (Mahkamah Rayuan)
- Court
- NCVC
- Case number
- R-02(NCVC)(W)-1356-07/2019 (Mahkamah Rayuan)
The Court held the completion period could not be fixed as running from signing prior to statutory approvals; approvals determined when the 24-month period could be measured, parties’ conduct and agreed extensions put time at large, D9's 30 June 2017 date was only an estimate, the Respondents were estopped from pursuing the suit after agreeing to withdraw, and the valuation evidence was inadmissible for non‑compliance with O.40A r.3; accordingly there was no proven delay or entitlement to damages and the appeal was allowed.