12 Jan 2023
Lembaga Lebuhraya Malaysia 1. ) MMC TEPAT TEKNIK SDN BHD 2. ) PENTADBIR TANAH DAERAH KLANG
- Citation
- 01(f)-19-05/2022(B) (Mahkamah Persekutuan)
- Court
- f
- Case number
- 01(f)-19-05/2022(B) (Mahkamah Persekutuan)
Buildings and losses related to those buildings are not compensable because at the acquisition date the buildings were not permitted under State land law and local planning law; paragraph 1(3A) of the First Schedule to Act 486 requires disregarding value of such buildings, section 9A makes planning information conclusive for valuation, and an amnesty or asserted legitimate expectation cannot override statutory provisions; accordingly appeals by Lembaga Lebuhraya Malaysia were allowed and MMC Tepat Teknik's appeal dismissed with costs.