CHONG BOON SAN 1. ) MUJUR ZAMAN SDN BHD 2. ) MZ DEVELOPMENT SDN. BHD. BUKAN PIHAK-PIHAK Chin Chan Leong
- Citation
- BA-22NCvC-315-08/2022 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-22NCvC-315-08/2022 (Mahkamah Tinggi)
The Court found the Sale & Purchase Agreement was executed after commencement of a winding up petition against the 2nd Defendant and before its winding up, rendering the disposition void under s223 and voidable as an undue preference under s293 (no valuable consideration, contra arrangement within the two-year twilight); the winding up occurred after the contract such that frustration principles apply; however the Plaintiff's claims are time-barred because causes of action accrued no later than 15.12.2014 and suit filed in 2022, and s29 does not extend limitation where the relevant facts were…