14 Mar 2022
BA-22NCC-103-08/2021 (Mahkamah Tinggi)
- Citation
- BA-22NCC-103-08/2021 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-22NCC-103-08/2021 (Mahkamah Tinggi)
Summary judgment was dismissed because the defendant established triable issues of fact—primarily whether the contract required supply plus installation, testing and commissioning and whether plaintiff completed the works—which could not be resolved on affidavit evidence and required viva voce evidence at trial.