24 Apr 2026
SOONG MENG SERVICE SDN. BHD. SEJATI ELIT SDN. BHD.
- Citation
- BD-B52-8-11/2024 (Mahkamah Sesyen)
- Court
- Sessions Court
- Case number
- BD-B52-8-11/2024 (Mahkamah Sesyen)
Clause 25 (force majeure) could not be relied upon because the developer failed to give the prompt written notice required by the clause; clause 19.1’s LAD provision was subject to the purchaser having paid all instalments and the purchaser had not paid the outstanding RM169,850 before filing so the LAD claim was premature; parties’ conduct demonstrated the 24‑month completion term was not treated as operative by them; on balance neither party proved its case and both the original claim and counterclaim were dismissed with costs to be borne respectively.