17 Jan 2024
Dinding Development Sdn Bhd (Dalam Likuidasi) CITYVILLA CONSTRUCTION SDN BHD
- Citation
- JA-24NCvC-1064-09/2023 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- JA-24NCvC-1064-09/2023 (Mahkamah Tinggi)
The application was dismissed because the applicant sought declarations and orders affecting defendants (D2–D4) whose JIDs had not been set aside by them in the proper proceedings; the court could not, in these proceedings, make orders binding those defendants or government departments (per s54 Specific Relief Act 1950) without the correct procedural steps having been taken.