29 Aug 2022
YOU CONSTRUCTION WORKS SDN BHD RAJESWARAN PARAMJOTHY
- Citation
- AA-A52NCvC-76-07/2018 (Mahkamah Sesyen)
- Court
- Sessions Court
- Case number
- AA-A52NCvC-76-07/2018 (Mahkamah Sesyen)
The court found on the balance of probabilities that Plaintiff completed the works as certified by the architect appointed by Defendant, Defendant failed to give timely or corroborated notice of defects within the defect liability period and did not dispute the sum owing, therefore Defendant breached the contract and is liable to pay the outstanding sum of RM124,615.25 together with costs and statutory interest.