25 Nov 2020
GLOCAL TECH ENGINEERING SDN BHD PANZANA ENTERPRISE SDN BHD
- Citation
- WA-24C-153-07/2020 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-24C-153-07/2020 (Mahkamah Tinggi)
The application was dismissed because the plaintiff failed to prove MKP had not paid the adjudicated amount and the defendant discharged the evidential burden under s 30(5) by showing there was no money due or payable to MKP at the time of receipt of the s 30 request (pending Suit 421 with substantial counterclaims); therefore the mandatory precondition in s 30(5) was not satisfied and s 30 could not be invoked to compel direct payment.