20 Jun 2022
GOLD PRESTIGE DEVELOPMENT SDN BHD UNILINK SDN BHD
- Citation
- BA-22C-13-04/2022 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-22C-13-04/2022 (Mahkamah Tinggi)
Defendant failed to discharge the burden to show any triable issue; contractual provisions (clauses 2.1 and 3.2) are clear as a matter of law; documentary admissions, payment records and Defendant's own confirmed construction cost summary estop Defendant from denying liability; counterclaim is not bona fide and does not defeat summary judgment; therefore summary judgment granted for unpaid fees and balance cost saving with contractual interest and costs.